Concrete pour rate

Placed per hour
m³/h
Buckets an hour
In the shift
Buckets in the shift

What it holds on the day, not what is painted on the side.
4.0
The whole lap, in minutes.

About this tool

Bucket size and the round trip, in — how much concrete an hour and how much lands in a shift, out. In metres and in yards.

How it is worked out

  • Buckets an hour = 60 ÷ the round trip in minutes
  • Concrete an hour = bucket size × buckets an hour
  • In the shift = concrete an hour × the hours you are pouring

There is no fudge factor in there, and that is on purpose. If you want an allowance for breaks, a late truck or the pump arriving, put it in the shift hours where you can see it — a hidden efficiency percentage is how a pour plan quietly becomes fiction.

What decides the cycle

  • The distance and the height. A bucket going up forty floors and out sixty metres is a different lap from one crossing a slab on grade.
  • Who is on the end of it. A crew that lands the bucket, dumps and clears in fifteen seconds beats one that takes a minute, every single lap, all day.
  • The trucks. The crane cannot go faster than the concrete arrives. Work out the rate here, then check how many trucks an hour that actually needs.
  • Wind and visibility. Both slow a cycle down long before either stops the job.

Metres and yards

A cubic yard is 0.764 554 857 984 cubic metres exactly — about three quarters. Concrete is ordered in cubic metres here and cubic yards over the line, and on a small pour the difference between the two is a whole truck. The unit converter has it if you need it on its own.

This is the crane’s rate, not the pour’s. Time the whole cycle with a stopwatch over ten buckets and put the average in — one good cycle is not a rate.