Notice of Project for a tower crane in BC
Putting a tower crane up is not a job you start and sort the paperwork out afterwards. Here is what has to exist before the first section leaves the yard.
The Notice of Project
A Notice of Project is submitted to WorkSafeBC before certain work begins. Erecting a tower crane is one of the triggers, and it is filed in advance rather than on the day. Keep the NOP number — a general contractor or an officer will ask for it, and "we filed one" is not an answer.
What sits alongside it
- The engineered foundation certificate. The foundation has to be inspected before the pour by a professional engineer or their designate, and that inspection has to be in writing. This one holds jobs up more than any other.
- A signed erection plan for that crane on that site, not a generic one.
- The pre-job meeting, held with everybody who will be on site for the lift, and minuted with who attended.
- The trucking and delivery plan, and the exclusion zone around the lift.
- The mobile crane doing the erecting, with its own paperwork current.
- Power lines — checked, with the clearances confirmed before anything is lifted.
- The forecast. The wind limit for erecting is far lower than the wind limit for working, and it is the number people get wrong. Our machines lift at a lower limit when being erected, climbed or dismantled than when they are in service.
Subcontracting the lift does not move any of this. If you hire a crew to erect your crane, their method and their people are theirs — but the condition of the machine, its records, and the two checks that fall due after they drive away remain yours.
What a general contractor will ask you for
In roughly this order: the crane's current annual inspection, the operational test, the foundation certificate, the NOP number, the erection plan, and proof of insurance. If you can send those from a phone the same day, you look like a different company from the one who says they will dig it out.
Related guides
- Tower crane wind limits — working, erecting and out of service are three different numbers.
- Tower crane records you have to keep — what to hold per machine, and what a contractor asks for first.
- All of our tower crane guides — inspection, maintenance and paperwork in British Columbia.
Every machine comes with its inspection and service record kept against it, and we send the certificates the day you ask. If you need a crane, or a hand with the paperwork on one you already have, get in touch.